Provison of Rigid Pipeline and Flexible Flowline transportation and Laying, Tie-in, Subsea Installation and Pre-commissioning Works
- Laying Flowline and submarine cable from 21/3 to 22/4:
- 2.8 kmsubsea umbilical from WHP DH01 to FPU balcony
- 2.9km 6inch Flexible from WHP DH01 to FPU balcony
- 16/4-23/5 Tie-in Spools
- 2.9km 8inch Flexible from WHP DH01 to FPU balcony
2. Tie-in Spools from 16/4 to 23/5
- 12inch Rigid Spool tie-in at WHP DH01
- 10 inch Rigid Spool tie-in at WHP DH01
- 8 inch Rigid Spool tie-in at WHP DH01
- 6 inch Rigid Spool tie-in at WHP DH01
- 12 inch Rigid Spool tie-in at WYE
- 16 inch WYE Skid removal
- 16inch Barred Tee Spool installation
3. Pre-commissioning from 26/4 to 03/6
- Flooding and dewatering for 16inch existing PL from DH02 to BK TNG
- Dewatering for 12inch PL from WYE TEE to WHP DH01
- Flooding, Cleaning, Gauging and hydrotesting for 6inhc, 8 inch, 10 inch Flowline from WHP DH01 to FPU
- Dewatering for 6inch flexible from WHP DH01 to FPU