Client: MODEC/POS
Work location: Rang Dong oil field
Water depth: 58m
Offshore Time: May 2018
Vessel: Pacific Diligence, PTSC Ha Long & TC 89
Equipment: WROV Quantum 3 & Rigging gear
Project SOW:
- Load out and transport all mooring leg components from onshore Vung Tau to offshore site.
- Receipt of existing Top Chain from FSO MV17, recover existing mooring leg components.
- Pre-tension (soil cutting) for nine (09) Pile Chains and Anchor Piles by OCV;
- Connect remaining components of new mooring legs to Pile Chains and laying;
- Hold FSO MV17 during disconnection of existing mooring legs and hook-up of new mooring legs using Heading Control Tug
- Transfer and handover new mooring legs to FSO MV17 Turret and pull into Chain stopper and hang off;
- Dispose existing chain.
Transfer wire from Drums to OCV Spool and storage chain into chain locker Disconnect and reciver existing chain on ROV vessel Disconnect and transfer existing chain from Turret Reconnect new chain and handover back to FSO MV17