As per Lumpsum Contract between PVEP POC & TOS, TOS used to TOS Ha Long for plug & abandonment of DH-1P, DH-2P, DH-3P well.
TOS Ha Long was towed at 10:30hrs, July 16th 2020 from PVC-MS Port and arrived the DH-1P location at 08:30hrs July 18th 2020. The P&A operation was completed at 09:00hrs 21st November, 2020.
Well Data
Surface Geographical Location Heading | 8°29’19” 106N 108°40’37” 670N 227.5° |
P&A Unit Contractor | TOS HA LONG TOS |
Elevation R.T.E – M.S.L M.S.L – Seabed | 11.7 m 109.3m |
Commencement of P&A Completion of P&A | 08:30hrs on July 18th 2020. 09:00hrs on November 21st 2020. |
Total Plan Time | 75 Days |
Final Well Status | Permanent Abandonment |
Final Seabed Survey | No Debris confirmed by ROV |